It is the responsibility of the zoning officer to make sure the City of Wright City Codes are followed in regards to all areas other than those of the Police Department, such as grass and weeds, trash, junk, parking of boat and trailer, campers, and utility trailers.
Wright City Building Department
The Building Department is here to provide quality service to all customers in regards to inspections and plan review for our customers while maintaining our goal to protect the health, safety, and welfare of our city residents. The City is under the 2015 IBC and IRC building codes as well related codes; if you have other questions please contact the building department. All apartments and single-family housing units must obtain an inspection and occupancy permit prior to taking up residency.
To schedule an inspection, call City Hall at 636-745-3101 at least twenty-four (24) hours in advance of requested time, between 8am-5pm Monday – Friday.
Contact Us
Lance Bauer
Building Inspector
Phone: (636) 745-3101
Email: buildinginspector@wrightcity.org
Building Permit Application Requirements
- Completed Building Permit Application
- Submit the following:
- Two (2) complete set of wet seal plans
- Plot plan showing structure, front building line, side lines and rear lot line along with all easements
- Master Plans Review
- 1st time residential Plan submittal, once approved;
- Permit Application with plan name or number
- Plot Plan
Commercial Plans
- Two (2) complete sets of plans with wet seal, containing the following detailed pages, including a cover sheet stating use, occupant load, type of construction, height and area; Structural, Mechanical, Plumbing, Electrical, and Sprinkler system.
- Determination of Planning and Zoning Regulations
- Determination of Flood Area
- Applicant certifies information is correct and in compliance with the City of Wright City.
- Failure to comply with City Building Codes will result in a Stop Work Order till such time a solution is reached
- Developer/Contractor is responsible to check with other agencies to acquire any permits needed from them such as DNR, FEMA.
Note: Builder will need a permit from Fire Department for major construction also.